Kosmos Energy Anticipates Possible Q2 2024 Start for Tortue LNG Project
(Reuters) — Kosmos Energy said on Monday that the start-up of the BP-operated Greater Tortue Ahmeyim (GTA) gas project offshore Senegal and Mauritania could slip into the second quarter of 2024.
BP last week said that the project was 90% complete and is expected to start production in the first quarter, slightly later than originally planned after BP replaced the contractor for its subsea pipeline system.
The Floating Production Storage and Offloading (FPSO) for the GTA project is en route to the field and is expected to arrive in the first quarter of next year, Kosmos said in its third quarter earnings results.
Kosmos said that the timing of production start-up now depends on the arrival, hook-up and commissioning of the FPSO as well as the floating liquefied natural gas (FLNG) facility.
"The delivery of first gas in the first quarter of 2024... depends on the execution of this workstream, which has the potential to slip into the second quarter of 2024."
BP declined to comment on Kosmos' update.
BP holds a 56% stake in the GTA project, while Kosmos holds a 26.8% share.
Phase 1 of the project will produce 2.5 million tonnes per year of LNG.
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Boardwalk Approves 110-Mile, 1.16 Bcf/d Mississippi Kosci Junction Pipeline Project
- Kinder Morgan Approves $1.4 Billion Mississippi Crossing Project to Boost Southeast Gas Supply
- Colonial Shuts Largest U.S. Gasoline Pipeline to Investigate Leak
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Enbridge Should Rethink Old, Troubled Line 5 Pipeline, IEEFA Says
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Polish Pipeline Operator Offers Firm Capacity to Transport Gas to Ukraine in 2025
Comments