Regas Ship Arrives for Hong Kong's First LNG Import Terminal
(Reuters) — The world's largest floating storage and regasification unit (FSRU) has arrived in Hong Kong to serve the city's first LNG import terminal, said CLP Power Hong Kong Ltd and Hong Kong Electric Co. Ltd.
The FSRU arrived on April 13 and will set sail after checks and port clearance procedures to the offshore Hong Kong LNG terminal next week for final commissioning of the project, the two companies said in a joint statement on Thursday evening.
The 4 million tonnes a year import terminal project has been delayed by more than two years as the COVID-19 pandemic slowed construction.
To be renamed the Bauhinia Spirit, the FSRU owned by Mitsui O.S.K. Lines 9104.T and Vopak, is 345 meters long and has storage capacity of 263,000 cubic meters.
The vessel will be moored at the jetty of Hong Kong LNG terminal to receive, store and regassify LNG.
The LNG terminal, jointly developed by CLP Power and HK Electric, is scheduled to start operating in mid-2023. CLP Power last month issued a tender to purchase a commissioning cargo for the terminal for delivery in May.
Related News
Related News

- PG&E Reduces Emissions from Gas Pipelines by More Than 20%
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Spain's Tecnicas Reunidas, FCC to Build LNG Terminal Worth $1.1 Billion in Germany
- Canada Offers $26 Billion Green Tax Credits But Still Trails Behind US Incentives
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Permian In Spotlight as Energy Dealmaking Gathers Steam
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Colombia's Cano Limon-Covenas Pipeline Attacked for Ninth Time in 2023
- Chad Nationalizes Exxon’s 621-Mile Pipeline as Dispute Over Asset Sale Escalates
Comments