Canada's Trans Mountain Still 'Days Away' From Restarting Pipeline

(Reuters) — Canada's Trans Mountain said on Monday it was "still days away" from restarting the key oil pipeline at a reduced capacity as heavy rains continue to impede restoration efforts.
The pipeline, owned by the Canadian government, ships 300,000 barrels a day of crude and refined products from Alberta to the Pacific Coast. It was temporarily shut down as heavy rains and flooding caused widespread disruption in parts of British Columbia.
The operator said assessments of the impacts from the latest storm are being undertaken with a focus on the Coldwater and Coquihalla regions.
Work was interrupted at some sites on Sunday due to high water accumulation or lack of access, the company added.
The company on Friday had said it was working toward restarting the oil pipeline at a reduced capacity this week.
Related News
Related News

- PG&E Reduces Emissions from Gas Pipelines by More Than 20%
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Spain's Tecnicas Reunidas, FCC to Build LNG Terminal Worth $1.1 Billion in Germany
- Canada Offers $26 Billion Green Tax Credits But Still Trails Behind US Incentives
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Pipeline Operator TC Energy Says Keystone Oil Spill Caused by Fatigue Crack
- Permian In Spotlight as Energy Dealmaking Gathers Steam
- Trans Mountain Pipeline Expansion Project to Nearly Triple Current Capacity to 890,000 bpd
- Colombia's Cano Limon-Covenas Pipeline Attacked for Ninth Time in 2023
- Chad Nationalizes Exxon’s 621-Mile Pipeline as Dispute Over Asset Sale Escalates
Comments