T.D. Williamson Crews Isolate Burning NGL Pipeline for Repair
T.D. Williamson crews isolated a ruptured 14-inch natural gas liquids (NGL) pipeline while product continued to flare off, enabling repair while the system remained in service and creating the conditions for the fire to extinguish itself.
The west Texas pipeline exploded after it was hit by a third-party contractor excavating the right-of-way nearby. The explosion and massive fire that followed, which shot flames 300 feet into the air, injured four people, one critically, and destroyed the trencher and all other equipment within a 300-yard radius.
It was said at the time of explosion the concussion was felt (10) miles away. The responding fire department registered a temperature in excess of 1500*F.
The operator moved quickly to reroute product at a drastically lower flow rate. Within hours of the line strike, TDW had begun mobilizing equipment and personnel to the site, including eight hot tapping and plugging (HT&P) technicians who arrived from multiple TDW service centers in Texas, Oklahoma and California to provide around-the-clock coverage.
The team performed a double STOPPLE® operation to isolate the affected section. Sweeping the hot tap holes — a process that removes any metal chips or debris that could prevent the STOPPLE head from sealing securely — created a partial seal that caused the fire to bellow; when the STOPPLE heads were fully set, they robbed the fire of the NGL fumes fueling it, and the blaze extinguished itself.
Charles Parrish, TDW technical sales representative, West Region, Texas & New Mexico, said the company’s response included 40 individuals, seven operations centers and six departments from across the U.S.
Parrish said that full COVID-19 precautions were followed at every step.
“Everyone came together so efficiently that in less than six hours after the operator’s initial call the fittings were out the door,” Parrish said. “And it took less than one day on the job site to solve our customer’s problem, safely and successfully.”
Related News
Related News
- Trump Aims to Revive 1,200-Mile Keystone XL Pipeline Despite Major Challenges
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Boardwalk Approves 110-Mile, 1.16 Bcf/d Mississippi Kosci Junction Pipeline Project
- Kinder Morgan Approves $1.4 Billion Mississippi Crossing Project to Boost Southeast Gas Supply
- Colonial Shuts Largest U.S. Gasoline Pipeline to Investigate Leak
- Tullow Oil on Track to Deliver $600 Million Free Cash Flow Over Next 2 Years
- GOP Lawmakers Slam New York for Blocking $500 Million Pipeline Project
- Enbridge Should Rethink Old, Troubled Line 5 Pipeline, IEEFA Says
- Energy Transfer Reaches FID on $2.7 Billion, 2.2 Bcf/d Permian Pipeline
- Polish Pipeline Operator Offers Firm Capacity to Transport Gas to Ukraine in 2025
Comments