TC Energy to Begin Construction on NGTL Expansion Project
By Jason Cockerham, Digital Editor
(P&GJ) — TC Energy has received approval from the Canadian government for its 2021 NOVA Gas Transmissions Ltd. (NGTL) System Expansion Project.
The approval was expected to be granted earlier this year but was delayed due to the COVID-19 pandemic.
The NGTL is a 15,000-mile (25,000 kilometer) natural gas transmission system that ships gas from the Western Canadian Sedimentary Basin (WCSB) across Alberta and British Columbia (B.C.) to connection points on other pipeline systems.
TC Energy plans to add an additional 214 miles (344 kilometers) of 48-inch pipeline to the NGTL system along with three compressor stations along the existing pipeline.
The majority of the new pipe would run alongside the existing infrastructure.
TC Energy expects the project to cost about $2.3 billion with construction on the compressor stations to begin in December and pipeline construction to begin in January 2021.
The NGTL expansion project is part of a larger $9.9 billion infrastructure program currently underway which will add 3.5 Bcf/d of incremental delivery capacity to the system between 2020 and 2024.
Related News
Related News

- FERC Approves TC Energy's 1,377-Mile West Coast Pipeline Expansion
- Kinder Morgan to Buy NextEra’s 462-Mile Texas Pipeline System for $1.8 Billion
- Williams' Gas Pipeline in Idaho Ruptures, Company Challenges Explosion Allegations
- Biden Awards $7 Billion in Hydrogen Hub Money to 16 States
- Mountain Valley Pipeline Sues Protesters Hindering $7.2 Billion Construction Project
- UAE's ADNOC Awards $17 Billion of Contracts for Gas Project, Including Subsea Pipelines
- HVO: Fuel for the Future
- Analysis: Canada May Struggle to Recoup $26 Billion Cost of Trans Mountain Pipeline
- Biden Awards $7 Billion in Hydrogen Hub Money to 16 States
- TC Energy Names Ex-CEO as Chair of Oil Pipeline Business
Comments