Golar's FLNG Gimi Completes First LNG Offload to British Sponsor
4/17/2025
(P&GJ) — The FLNG Gimi has completed its first full LNG offload to the British Sponsor, marking a major milestone for Mauritania and Senegal as they enter the international gas market.
The offload triggers the final pre-Commercial Operations Date (COD) milestone bonus payment to Golar, under the terms of a commercial reset agreement signed in August 2024.
Golar said commissioning remains on track for a Q2 2025 COD. Once achieved, it will activate a 20-year lease and operate agreement, unlocking approximately $3 billion of adjusted EBITDA backlog attributable to Golar. COD will also initiate the recognition of contractual payments across Golar’s balance sheet and income statement.
Related News
Related News
Sign up to Receive Our Newsletter

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- DOE Considers Cutting Over $1.2 Billion in Carbon Capture Project Funding
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Newsom Seeks to Aid Struggling Refiners Following Valero’s California Exit
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments