FERC Approves 122-Mile Ridgeline Gas Pipeline Expansion in Tennessee
By Mary Holcomb, Digital Editor
(P&GJ) — The Federal Energy Regulatory Commission (FERC) has approved The Enbridge Inc.-sponsored Ridgeline Expansion Project, a 122-mile natural gas pipeline system designed to serve the Tennessee Valley Authority’s (TVA) new combined-cycle power plant in Morgan County, Tennessee.
FERC issued the certificate on April 2, 2025, following an application by East Tennessee Natural Gas LLC, a subsidiary of Enbridge Inc., under sections of the Natural Gas Act. The $1.1 billion project will provide up to 300,000 dekatherms per day (Dth/d) of firm transportation service and 95,000 Dth of Customized Delivery Service to TVA.
The pipeline expansion includes:
- 110 miles of 30-inch mainline and 4 miles of 30-inch header pipeline
- An 8-mile lateral pipeline
- Three new crossover pipelines
- A new compressor station in Trousdale County with 14,600 horsepower capacity
- Modifications to interconnects with other major pipelines (Texas Eastern, Columbia Gulf, and Midwestern Gas Transmission)
The infrastructure is critical to TVA’s plan to retire nine coal-fired units at its Kingston Plant by 2027 and replace them with a 1,500 MW natural-gas-fired plant, plus solar and battery storage systems.
East Tennessee signed a precedent agreement with TVA for 100% of the project’s capacity. The utility also proposed a new Customized Delivery Service feature to provide no-notice, flexible gas delivery up to 95,000 Dth/day, enabling rapid generation ramp-ups.
Pending regulatory approvals, the Ridgeline Expansion Project is on track to begin construction soon to meet TVA’s timeline.
The Author
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- 1,000-Mile Pipeline Exit Plan by Hope Gas Alarms West Virginia Producers
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Boardwalk’s Texas Gas Launches Open Season for 2 Bcf/d Marcellus-to-Louisiana Pipeline Expansion
- New Alternatives for Noise Reduction in Gas Pipelines
- Construction Begins on Ghana's $12 Billion Petroleum Hub, But Not Without Doubts
- DOE Considers Cutting Over $1.2 Billion in Carbon Capture Project Funding
- Valero Plans to Shut California Refinery, Takes $1.1 Billion Hit
- Newsom Seeks to Aid Struggling Refiners Following Valero’s California Exit
Comments