Gazprom CEO Sees No Solution to Nord Stream 1 Repair Delays Caused by Sanctions
(Reuters) — Gazprom sees no solution to an ongoing equipment issue at the Portovaya compressor station, part of the Nord Stream 1 pipeline that carries Russian gas to Germany, its CEO said on Thursday.
Gazprom has cut the capacity along the Nord Stream 1 pipeline to just 40% of usual levels in recent days citing the delayed return of equipment being serviced by Germany's Siemens Energy in Canada.
CEO Alexey Miller said sanctions were preventing the company from getting the equipment back. Germany dismissed that explanation as "unfounded".
He noted the company has lots of equipment for the pipeline which is due to undergo major maintenance next month and lambasted Siemens for being "silent" over the issue.
European companies, including Italy's ENI, Austria's OMV and Germany's Uniper reporting significant falls in supply of Russian gas on Wednesday and Thursday.
The Kremlin said on Thursday that the reduction in supply was not premeditated.
Related News
Related News

- Kinder Morgan Proposes 290-Mile Gas Pipeline Expansion Spanning Three States
- Three Killed, Two Injured in Accident at LNG Construction Site in Texas
- Tallgrass to Build New Permian-to-Rockies Pipeline, Targets 2028 Startup with 2.4 Bcf Capacity
- TC Energy Approves $900 Million Northwoods Pipeline Expansion for U.S. Midwest
- U.S. Moves to Block Enterprise Products’ Exports to China Over Security Risk
- U.S. Pipeline Expansion to Add 99 Bcf/d, Mostly for LNG Export, Report Finds
- Enbridge Adds Turboexpanders at Pipeline Sites to Power Data Centers in Canada, Pennsylvania
- Great Basin Gas Expansion Draws Strong Shipper Demand in Northern Nevada
- Cheniere Seeks FERC Approval to Expand Sabine Pass LNG Facility
- Heath Consultants Exits Locate Business to Expand Methane Leak Detection Portfolio
Comments