Federal Appeals Court Tosses Permit for Atlantic Coast Pipeline Station
RICHMOND, Va. (AP) — A federal appeals court has thrown out a permit needed by developers of the Atlantic Coast Pipeline to build a natural gas compressor station in a historic African American community in Virginia.
The unanimous ruling from a three-judge panel of the 4th U.S. Circuit Court of Appeals is a victory for opponents of a proposal to build the station in Union Hill, an unincorporated community that was founded by freed slaves after the Civil War.
Lead developer Dominion Energy said the compressor station would have far fewer air emissions and more air control monitoring than any other station in the country. But opponents argued that the State Air Pollution Control Board and Dominion did not carefully consider the project’s potential health effects on Union Hill residents.
During oral arguments before the 4th Circuit in October, lawyers for opponents of the project said the state failed to consider the “unequal treatment” of people who live near the proposed site for the compressor station. Opponents said they were concerned that exhaust from the station could cause harmful health effects on nearby residents, most of whom are African American.
Union Hill is in rural Buckingham County, about an hour's drive west of Richmond.
During the October hearing, Deputy Solicitor General Martine Cicconi said the Air Pollution Control Board "absolutely grappled" with the issue of environmental justice and carefully considered any adverse health impacts on residents. She said the emissions will fall well below emissions from other compressor stations in Virginia and will meet national ambient air quality standards.
The pipeline, which would run 600 miles (965 kilometers) and carry fracked natural gas from West Virginia into Virginia and North Carolina, has been mired in legal challenges by environmental and conservation groups. Construction has been halted since December 2018.
In its written ruling, the three-judge panel said it agreed with opponents that the board failed to assess the station's potential for disproportionate health effects on the community of Union Hill. The panel also said it agreed that the board failed to consider electric turbines as zero-emission alternatives to gas-fired turbines in the compressor station.
The 4th Circuit panel sent the case back to the Air Pollution Control Board.
Dominion said it will immediately begin working with the state to resolve the issues identified by the court.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- U.S. House Passes Bill to Reverse Biden's LNG Pause
- Mexico Orders Seizure of Hydrogen Plant at Pemex Oil Refinery
- EnCap Eyes $5 Billion Sale of Bakken Shale Producer Grayson Mill
- Sunoco to Acquire NuStar Energy in $7.3 Billion Deal for Midstream Expansion
- U.S. Regulators Approve Mexico Pacific LNG's Saguaro Connector Pipeline
- U.S. to Acquire 3 Million Barrels of Oil for Emergency Reserve in September
- AG&P LNG Acquires 49% Stake in Vietnam's Cai Mep LNG Terminal
- BP's Carbon Emissions Increase in 2023, Ending Decline Since 2019
- Texas Sues EPA Over Methane Emission Rules for Oil and Gas Sector
Comments