Vermont Gas: NatGas Pipeline Expected to be Finished in Spring
HINESBURG, Vt. (AP) — Vermont Gas Systems says it expects to finish building a roughly 40-mile natural gas pipeline this spring that will stretch from Colchester to Middlebury.
The utility tells Vermont Public Radio (http://bit.ly/2kgIwPn ) more than 2,000 feet of pipeline remain. The project involves drilling horizontally underneath a public park in Hinesburg.
The project was budgeted at $86.6 million in 2013. Its current budget is about $166 million.
Vermont Gas says it stayed within its budget this past quarter.
The state Supreme Court lifted a stay last year and allowed the utility to progress with construction despite pending litigation.
Vermont Gas has posted a $1 million bond to cover the cost of removing the pipeline and restoring the land in case the high court rules against it.
An appeal from Hinesburg neighbors is pending.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Williams Delays Louisiana Pipeline Project Amid Dispute with Competitor Energy Transfer
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Russian LNG Unfazed By U.S. Sanctions
Comments