REASNOR, Iowa (AP) — Authorities suspect arson in the latest burning of heavy equipment being used in the construction of the four-state Dakota Access pipeline in central Iowa.
The Jasper County Sheriff’s Office says the blaze late Saturday near Reasnor, Iowa, caused about $2 million damage to an excavator and three bulldozers. The equipment is operated by a contractor for Dakota Access, a subsidiary of Dallas-based Energy Transfer Partners.
Opponents have for months been protesting the $3.8 billion, nearly 1,200-mile project pipeline, warning its construction could jeopardize water supply and damage cultural artifacts.
Another suspected arson of construction equipment happened on Aug. 1 at the same site, about 30 miles east of Des Moines.
No arrests have been made in either fire. The Iowa Fire Marshal Division and the FBI are investigating.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Williams Delays Louisiana Pipeline Project Amid Dispute with Competitor Energy Transfer
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Russian LNG Unfazed By U.S. Sanctions
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
Comments