MVP Preparing to Weld Final 20 Miles, Targeting Summer 2022 In-Service Date
(P&GJ) – The total project work for Mountain Valley Pipeline (MVP) is nearly 94% complete and on track for a summer startup after state agencies approved construction permits in December. MVP, which is owned by Equitrans Midstream, NextEra Energy, Consolidated Edison, AltaGas and RGC Resources Inc., is a $6 billion project spanning 303 miles (488 km) across West Virginia and Virginia, which should deliver up to 2 Bcf/d (57 MMcm/d) of domestic natural gas. MVP’s originally estimated in-service date was in late 2018, but setbacks including legal challenges from states and environmental groups have delayed the in-service date multiple times. I