May 2021, Vol. 248, No. 5
Features
Ameren Illinois Begins Phase 2 Transmission Pipeline Upgrade
Special to Pipeline & Gas Journal Ameren Illinois began Phase 2 of a $65 million project to modernize its natural gas energy delivery infrastructure in and around Belleville, Ill., the company said. Photo: Ameren Beginning in early April, about 125 Ameren Illinois contractors started upgrading a 6-mile (10-km) stretch of natural gas transmission pipeline from Frank Scott Parkway/Concordia Church Road northwest to Illinois Route 13. Crews began replacing vintage steel transmission pipeline from the 1950s with new, 16-inch (406-mm) steel pipeline. Completion of the pipeline, expected by mid-September, will strengthen the integrity and rel