Pennsylvania Pipeline Work Resumes After $12M Fine, Changes
HARRISBURG, Pa. (AP) — Pennsylvania regulators are fining Sunoco more than $12 million for problems with a massive natural gas pipeline project, but letting work resume under a consent agreement.
The Department of Environmental Protection said Thursday that Sunoco Pipeline has made changes since work on the $2.5 billion Mariner East 2 pipeline was halted Jan. 3.
The 350-mile project has been plagued by spills and leaks of drilling fluid and improper construction methods.
In stopping the work, the state agency said Sunoco demonstrated it couldn’t or wouldn’t comply with Pennsylvania’s clean streams law and other regulations.
The company didn’t immediately respond to messages seeking comment.
The 20-inch pipeline will move natural gas liquid products from Marcellus Shale drilling fields in western Pennsylvania to a terminal in Philadelphia.
It’s scheduled for completion by summer.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- U.S. to Acquire 3 Million Barrels of Oil for Emergency Reserve in September
- AG&P LNG Acquires 49% Stake in Vietnam's Cai Mep LNG Terminal
- BP's Carbon Emissions Increase in 2023, Ending Decline Since 2019
- Texas Sues EPA Over Methane Emission Rules for Oil and Gas Sector
Comments