DES MOINES, Iowa (AP) — A district court judge has ruled against 14 Iowa landowners who sued to block the Dakota Access pipeline from crossing their property, concluding that the Iowa Utilities Board properly approved a permit for its construction.
Judge Jeffrey Farrell says in a decision filed Wednesday that the board adequately considered whether the pipeline provides a public convenience and necessity and its decision to grant a license was supported by state law and evidence.
The landowners challenged the board’s decision claiming it was illegal to take farmland for a pipeline that provides no public service to Iowans.
The pipeline moves oil out of North Dakota across South Dakota and Iowa and into Illinois.
Related News
Related News
Sign up to Receive Our Newsletter
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Russian LNG Unfazed By U.S. Sanctions
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments