Mountain Valley Pipeline Project to Be 70% Complete by Year-End
12/13/2018
PITTSBURGH – Mountain Valley Pipeline (MVP) officials said the company remains on target for the $4.6 billion project in fully in-service in the fourth quarter of 2019.
Mountain Valley expects to have 70% of the MVP project complete by year-end, which includes the welding of nearly 58% of the pipeline and the ongoing construction work of all compressor stations and interconnects that are expected to be complete by February.
Most recently, MVP construction crews have focused on stabilizing the right-of-way for the winter season.
“Despite various setbacks and unprecedented weather conditions, we have made substantial progress this year,” said Chief Operating Officer Diana Charletta, of Equitrans Midstream Corporation.
Related News
Related News
Sign up to Receive Our Newsletter
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- U.S. House Passes Bill to Reverse Biden's LNG Pause
- Mexico Orders Seizure of Hydrogen Plant at Pemex Oil Refinery
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- MEG Energy Confirms Trans Mountain Pipeline Expansion to Begin Line Fill in April
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025
Comments