Turkish Permit for Land Section of TurkStream Pipeline Still Pending
4/3/2018
ANKARA (Reuters) - Russian Energy Minister Alexander Novak said on Tuesday that Turkey's approval for Gazprom's onshore portion of the TurkStream gas pipeline's second line is still pending.
"As for the onshore part, this is now at the discussion stage... the (Russian and Turkish) companies are discussing the protocol," Novak told reporters.
All permissions for the offshore part had been received and it was under construction, he said.
Sources told Reuters in February that Turkey has yet to issue a permit for Gazprom to start building the land-based part of the TurkStream gaspipeline, stoking fears the project may be delayed.
Related News
Related News
Sign up to Receive Our Newsletter
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Williams Delays Louisiana Pipeline Project Amid Dispute with Competitor Energy Transfer
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Russian LNG Unfazed By U.S. Sanctions
Pipeline Project Spotlight
Owner:
East African Crude Oil Pipeline Company
Project:
East African Crude Oil Pipeline (EACOP)
Type:
TotalEnergies in discussions with a Chinese company after Russian supplier Chelpipe was hit by sanctions.
Length:
902 miles (1,443 km)
Capacity:
200,000 b/d
Start:
2022
Completion:
2025