Enbridge Asked to Revise Environmental Impact Statement for Line 3 Replacement Project
(Reuters) — Enbridge Inc needs to add an analysis of potential oil spills into Lake Superior watershed and submit a revised environmental impact statement (EIS) to proceed with its Line 3 pipeline replacement project, a Minnesota regulator said on Tuesday.
The order from the Minnesota Public Utilities Commission comes as the company struggles with delays amid ongoing disputes with regulators. Enbridge has 60 days to submit its revised EIS.
The commission was ordered to revise Enbridge’s EIS for the project in June after a court determined the previous assessment was inadequate.
Line 3, part of Enbridge’s Mainline network that transports western Canadian crude oil to Midwest refineries, is expected to be in service by the second half of 2020 but many oil industry participants are concerned it will be delayed beyond that.
The project would double capacity to 760,000 barrels per day, providing much-needed relief from congestion on existing Canadian pipelines.
Enbridge was also recently ordered to stop its Mainline overhaul plan due to the “perception of abuse of Enbridge’s market power” by the Canadian Energy Regulator.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- Biden Administration Buys Oil for Emergency Reserve Above Target Price
- Freeport LNG Plant Runs Near Zero Consumption for Fifth Day
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Evacuation Technologies to Reduce Methane Releases During Pigging
- Editor’s Notebook: Nord Stream’s $20 Billion Question
- Enbridge Receives Approval to Begin Service on Louisiana Venice Gas Pipeline Project
- Mexico Seizes Air Liquide's Hydrogen Plant at Pemex Refinery
- Russian LNG Unfazed By U.S. Sanctions
Comments