Kinder Morgan Moves Ahead with Pipeline Connection to Houston
HOUSTON (Reuters) - Kinder Morgan Inc will go ahead with a South Texas pipeline connection that would transport crude from Phillips 66's 900,000 bpd Gray Oak pipeline in the Permian Basin to delivery points at the Houston Ship Channel, the company said on Wednesday.
The pipeline operator expects the connection will begin service by the end of 2019 carrying 100,000 bpd. Kinder and Phillips began soliciting shipper commitments for the connection in February.
The company plans to spend $10 million on the project this year and has contracts to start transporting 75,000 bpd for up to three years, Chief Executive Officer Steven Kean told investors.
"We wanted to find a way to get Permian barrels to KMCC (Kinder Morgan Crude and Condensate pipeline)," which delivers crude from the Eagle Ford Shale in South Texas to Houston Ship Channel destinations, Kean said.
The company is also considering converting an underutilized natural gas pipeline to carry crude from the Bakken shale in North Dakota and the Denver-Julesburg basin in Colorado.
The ongoing startup of the company's Elba Island liquefaction facility may have to be suspended because of problems that have emerged in its supercooling equipment that produces liquefied natural gas, but it expects to bring the first unit into service soon, Kean said.
Related News
Related News
- Keystone Oil Pipeline Resumes Operations After Temporary Shutdown
- U.S. House Passes Bill to Reverse Biden's LNG Pause
- Mexico Orders Seizure of Hydrogen Plant at Pemex Oil Refinery
- Enbridge to Invest $500 Million in Pipeline Assets, Including Expansion of 850-Mile Gray Oak Pipeline
- MEG Energy Confirms Trans Mountain Pipeline Expansion to Begin Line Fill in April
Comments